- Location
- 89 Eccleston Square, London SW1V
- Status
- Mobilising
- Our role
- Electrical contractor
- Size
- 297 guest rooms
- Building
- Nine-storey office, 1960s–70s
- Enabling works
- Complete, August 2026
- Main package
- On site from October 2026
- Sector
- Hospitality
The development
Globe House is a nine-storey former government office building on the corner of Bridge Place and Belgrave Road, a short walk from Victoria station. It is being converted into a hotel with active ground-floor uses.
S&M is responsible for the electrical package described here, not the wider development.
Coordination
The temporary supplies were needed while the building was still being surveyed, so each had a defined source, route, isolation point and handover. Lift isolations were agreed with the lift contractor and held under lock-off for the survey.
For the main package we returned a fully quantified schedule of rates against the Stage 4 specification and listed document conflicts for the design team to resolve before pricing was fixed.
Our scope
- 01Temporary three-phase 63A supply to the roof building maintenance unit: a new way in the machine-room services board, cabling on existing containment and external brickwork, and an IP-rated roof outlet with metering and isolation.
- 02Isolation and lock-off of the lift supplies to allow a lift survey.
- 03Activity-specific RAMS, circuit identification and a plain-English installation report.
- 04Main electrical package to circulation areas and guest rooms, starting October 2026.
Need enabling supplies or a full package?
We set up temporary supplies for surveys, plant and access equipment, then stay on for the main works.